§ 17.16.17.010. Application and review procedure.  


Latest version.
  • A.

    Submittal of application. The applicant shall submit a completed application to the Planning and Community Development Department along with the application fee as may be established by the City Commission.

    B.

    Determination of completeness. Within five (5) days of submittal, the Director of Planning and Community Development shall determine whether the submitted application is complete or incomplete and notify the applicant, in writing, of any deficiencies. If the application is deemed incomplete, the applicant has twenty (20) days to resubmit the application or forfeit the application fee. The director shall take no further steps to process the application until the deficiencies are remedied.

    C.

    Determination of compliance. Within three (3) days after a determination of completeness, the director shall approve the application, approve it with conditions, or deny the permit based on the decision criteria established in this article.

    D.

    Resubmittal of application. If the application is denied, the applicant has twenty (20) days to submit another application or forfeit the original application fee.

(Ord. No. 3056, § 1, 8-17-2010)